Update inputs/manual_input.csv
Browse files Browse the repository at this point in the history
Co-authored-by: euronion <42553970+euronion@users.noreply.github.com>
  • Loading branch information
fneum and euronion committed Dec 14, 2023
1 parent 522a241 commit b905875
Showing 1 changed file with 1 addition and 1 deletion.
2 changes: 1 addition & 1 deletion inputs/manual_input.csv
Original file line number Diff line number Diff line change
Expand Up @@ -17,7 +17,7 @@ H2 (g) pipeline,FOM,2050,1.5,%/year,2015,"Danish Energy Agency, Technology Data
H2 (g) pipeline,electricity-input,2020,0.021,MW_e/1000km/MW_H2,2015,"Danish Energy Agency, Technology Data for Energy Transport (2021), Excel datasheet: H2 140.","Assumption for a 140 bar, 5-20 GW pipeline. Electric compression."
H2 (g) pipeline,electricity-input,2030,0.019,MW_e/1000km/MW_H2,2015,"Danish Energy Agency, Technology Data for Energy Transport (2021), Excel datasheet: H2 140.","Assumption for a 140 bar, 5-20 GW pipeline. Electric compression."
H2 (g) pipeline,electricity-input,2050,0.017,MW_e/1000km/MW_H2,2015,"Danish Energy Agency, Technology Data for Energy Transport (2021), Excel datasheet: H2 140.","Assumption for a 140 bar, 5-20 GW pipeline. Electric compression."
H2 (g) pipeline repurposed,investment,2020,154.79,EUR/MW/km,2020,European Hydrogen Backbone Report (June 2021): https://gasforclimate2050.eu/wp-content/uploads/2021/06/EHB_Analysing-the-future-demand-supply-and-transport-of-hydrogen_June-2021.pdf Table 35. Implementation roadmap - Cross border projects and costs updates: https://ehb.eu/files/downloads/EHB-2023-20-Nov-FINAL-design.pdf Table 1,"Assumption for 48-inch single line pipeline, incl. compressor investments, 16.9 GW peak capacity, 880 EUR/m, 434 MWe/1000 km for compressor, 4 MEUR/MWe for compressor."
H2 (g) pipeline repurposed,investment,2020,154.79,EUR/MW/km,2023,European Hydrogen Backbone Report (June 2021): https://gasforclimate2050.eu/wp-content/uploads/2021/06/EHB_Analysing-the-future-demand-supply-and-transport-of-hydrogen_June-2021.pdf Table 35. Implementation roadmap - Cross border projects and costs updates: https://ehb.eu/files/downloads/EHB-2023-20-Nov-FINAL-design.pdf Table 1,"Assumption for a 48 inch single line repurposed pipeline, incl. compressor investments, 16.9 GW (LHV) peak capacity (source 2), 0.8 MEUR/km base cost with additional investment for compressors of capacity 434 MWe/1000 km (source 1), at 4 MEUR/MWe for compressor (source 2)"
H2 (g) pipeline repurposed,lifetime,2020,50,years,2015,"Danish Energy Agency, Technology Data for Energy Transport (2021), Excel datasheet: H2 140.",Same as for new H2 (g) pipeline.
H2 (g) pipeline repurposed,FOM,2020,4,%/year,2015,"Danish Energy Agency, Technology Data for Energy Transport (2021), Excel datasheet: H2 140.",Same as for new H2 (g) pipeline.
H2 (g) pipeline repurposed,FOM,2050,1.5,%/year,2015,"Danish Energy Agency, Technology Data for Energy Transport (2021), Excel datasheet: H2 140.",Same as for new H2 (g) pipeline.